The projected timeline for the repair of the 96th Street Bridge has changed. The original project timeline had the bridge being in full operation by the summer of 2029, but the new schedule has the project wrapping in the summer of 2030.
Now, in the fall of 2028 to the spring of 2029, the drawbridge and span will be demolished. No traffic will be able to cross during this time, but there will be unlimited boat clearance. This phase is when the major closure will occur.
That summer, a temporary fixed span will be installed, allowing traffic to cross and there will be an 11-foot, 4-inch clearance for scheduled boat access. From the fall of 2029 to the spring of 2030, a new drawbridge and span will be installed. In the summer of 2030, testing will begin, and then the bridge should be in full operation.
This project is a long time coming for Stone Harbor and will improve both marine and traffic access to the island once completed. The good news for residents and visitors alike is that vehicles are expected to be able to cross from one side to the other during the summers of 2029 and 2030.
For updates, visit stoneharbornj.org. |